Ten construction Weifang polypropylene project into the commissioning stage

"
source: China Petrochemical News Network 2022-01-20 09:03

On January 18, the 300,000 tons/year high-end polypropylene project in Weifang, Shandong Province, which was built by the tenth construction Company of Refining and Chemical Engineering, realized the main completion target, marking that the project entered the preparation stage of commissioning from the project construction.

It is understood that Shandong Weifang 300,000 tons/year high-end polypropylene project is the key construction project of ten construction company in 2021, and the construction period is only 330 days. Since the start of the project, the Weifang Project Department of Ten construction Company has organized civil engineering, installation, electrical instrumentation and other professional construction technology leaders, jointly with owners, designers and other units, to deeply plan the construction of high-end polypropylene projects, carry out all-round and three-dimensional control of the safety, quality and progress of the project construction, and make every effort to create favorable conditions for the smooth implementation of the project.

In the construction process, the project department set up an expert group to conduct in-depth discussion on the key work of modular construction of steel structure, automatic pipeline welding, factory prefabrication, project digital management, etc., through the strategy of ""management innovation, efficiency improvement"", to provide strong technical support for project construction. To ensure that the construction of each professional quality, efficient, on schedule to complete the node target.

After 11 months of striving, the project department has completed more than 30,000 cubic meters of high-end polypropylene project concrete pouring, 3,500 tons of steel structure installation, 252 equipment installation, process pipeline welding 250,000 inches of construction tasks.

At present, the staff of the project department closely cooperate with the workshop staff of the owner to do the preparation work for the high-end polypropylene equipment to ensure that the project will be put into operation in mid-February.